Centre clears Dulhasti Stage-II power project in Kishtwar
August 25, 2026
  • Read Ecopy
  • Circulation
  • Advertise
  • Careers
  • About Us
  • Contact Us
Android AppiPhone AppArattai
Organiser
  • ‌
  • Bharat
    • Assam
    • Bihar
    • Chhattisgarh
    • Jharkhand
    • Maharashtra
    • View All States
  • World
    • Asia
    • Europe
    • North America
    • South America
    • Africa
    • Australia
  • Editorial
  • International
  • Opinion
  • RSS @ 100
  • More
    • Op Sindoor
    • Analysis
    • Sports
    • Defence
    • Politics
    • Business
    • Economy
    • Culture
    • Special Report
    • Sci & Tech
    • Entertainment
    • G20
    • Azadi Ka Amrit Mahotsav
    • Vocal4Local
    • Web Stories
    • Education
    • Employment
    • Books
    • Interviews
    • Travel
    • Law
    • Health
    • Obituary
  • Subscribe
    • Subscribe Print Edition
    • Subscribe Ecopy
    • Read Ecopy
  • ‌
  • Bharat
    • Assam
    • Bihar
    • Chhattisgarh
    • Jharkhand
    • Maharashtra
    • View All States
  • World
    • Asia
    • Europe
    • North America
    • South America
    • Africa
    • Australia
  • Editorial
  • International
  • Opinion
  • RSS @ 100
  • More
    • Op Sindoor
    • Analysis
    • Sports
    • Defence
    • Politics
    • Business
    • Economy
    • Culture
    • Special Report
    • Sci & Tech
    • Entertainment
    • G20
    • Azadi Ka Amrit Mahotsav
    • Vocal4Local
    • Web Stories
    • Education
    • Employment
    • Books
    • Interviews
    • Travel
    • Law
    • Health
    • Obituary
  • Subscribe
    • Subscribe Print Edition
    • Subscribe Ecopy
    • Read Ecopy
Organiser
  • Home
  • Bharat
  • World
  • Operation Sindoor
  • Editorial
  • Analysis
  • Opinion
  • Culture
  • Defence
  • International Edition
  • RSS @ 100
  • Magazine
  • Read Ecopy
Home Bharat

J&K: After Indus Treaty freeze, centre clears 260 MW Dul Hasti stage II project on Chenab; Work to be completed by 2029

The Union Ministry of Environment, Forest and Climate Change (MoEFCC) has approved the construction of the second stage of the Dul Hasti hydropower project on the Chenab River in Kishtwar district. This 260 MW project is being defined as an extension of the Dul Hasti hydropower project, which has been operating successfully since 2007

Sant Kumar SharmaSant Kumar Sharma
Dec 27, 2025, 04:00 pm IST
inBharat, Jammu and Kashmir
Follow on Google News
The Salal Hydro Power project dam on India’s Chenab river in Riasi

The Salal Hydro Power project dam on India’s Chenab river in Riasi

Facebook
Twitter
WhatsAppTelegramEmail

JAMMU: The Environmental Appraisal Committee (EAC) under the Union Ministry of Environment, Forest and Climate Change (MoEFCC) has approved the Dulhasti Stage-II hydroelectric project (260 MW) in the Kishtwar district of Jammu and Kashmir, with a project cost of Rs 3,277.45 crore. The clearance was granted on December 19, a week earlier, and the proposed project has been defined as an extension of the 390 MW operational Dul Hasti I. The first stage of the project was commissioned in the year 2007 and has been operating successfully since then.

The National Hydroelectric Power Corporation (NHPC) had entered into a Memorandum of Understanding (MoU) with the government of the Union Territory (UT) of Jammu & Kashmir on January 3, 2021, almost four years ago, for the execution of the Dul Hasti Stage II hydroelectric project on Build Own Operate Transfer (BOOT) basis for a period of 40 years.

Also Read: Zoho-backed VoxelGrids unveils first Indigenous 1.5T MRI scanner, slashes costs & boosts Aatmanirbhar Bharat push

This project will utilise water from the Chenab River, part of the Indus Water Basin. The EAC noted that the project’s parameters have been planned in compliance with the provisions of the Indus Water Treaty (IWT) of 1960. However, the Treaty was put in abeyance on April 23 this year after the Pahalgam terrorist attack.

The new project will draw water from the Dulhasti Power Station (Stage I) through a separate 3,685-meter-long tunnel with a diameter of 8.5 meters, leading to the construction of a horseshoe pondage for Stage II. In addition to constructing the pondage, the project will include a surge shaft, a pressure shaft, and an underground powerhouse equipped with two 130 MW units, for a total installed capacity of 260 MW and annual energy generation.

The total land requirement for the project is estimated at 60.3 hectares. This project will require 8.27 hectares of private land from two villages, Benzwar and Palmar, in the Kishtwar district. The land acquired earlier for stage I of the project will also be used for setting up of the second stage.

At the time of granting environmental clearance, the EAC directed that a study be undertaken five years after the project’s commissioning to assess its environmental impact. “After five years of commissioning of the project, a study shall be undertaken regarding the impact of the project on the environment. An independent agency shall undertake the study,” the official meeting held on Friday last noted.

The ministry has also directed NHPC and Chenab Valley Power Projects Limited (CVPPL) to undertake a study, in collaboration with a reputable government research institute, to formulate a strategy for sustainable environmental management of the Chenab River basin. The study will cover aspects such as scientifically robust environmental flow regimes, restoration and maintenance of channel morphology and sediment processes. It has also directed them to protect and conserve aquatic and riparian biodiversity, address livelihood and community concerns, and integrate the Marusudar tributary of the Chenab within the Chenab basin cascade framework.

The Dul Hasti reservoir receives an average of 24 million tons of sediment per year, mostly from May to September, when water flow is high. Flushing and sluicing methods are used to manage sediment and maintain reservoir capacity.

This project is expected to be completed within 44 months (under four years) of contract award, but the actual timeline may vary, officials said. At present, due to the tendering process, which started in mid-2025 and the environmental clearance, it is likely to be completed by mid to late 2029. Incidentally, there is no forest land involved in the project and as such no clearances from the forest department is needed for land acquisition. As an extension of the existing NHPC project, it will use the already constructed dam and intake structure thereby avoiding the need for a new impounding structure..

Topics: Chenab Valley Power Projects LimitedDulhasti Power StationUnion Ministry of EnvironmentNational Hydroelectric Power CorporationNHPCForest and Climate ChangeEnvironmental Appraisal Committee
Share
Tweet
SendShareSend
✮ Subscribe Organiser YouTube Channel. ✮
✮ Join Organiser's WhatsApp channel for Nationalist views beyond the news. ✮
Previous News

“More than 2000 Maoists have surrendered in Chhattisgarh”: CM Vishnu Deo Sai hails state rehabilitation drive

Next News

Banaras to Mozambique, a journey of BLW swadeshi locomotive export post 2014

Related News

NHPC CMD Bhupender Gupta inaugurated construction activities of the 240 MW Uri-I Stage-II Hydroelectric Project in Uri

J&K eyes round-the-clock power supply: NHPC begins work on 240 MW Uri-I stage II project

External Affairs Minister S Jaishankar

Indus Water Treaty: “India has the right to defend its people from bad neighbour fostering terrorism,” says Jaishankar

Representative Image

J&K losing around Rs 12 crore daily on account of power theft, T&D losses of 48%, related inefficiencies in 2025-26

Sawalakote hydropower project

Sawalakote hydropower project faces challenges on financial, technical grounds: J&K CM Omar Abdullah

Representative Image

J&K: Global tender for largest hydropower 1,856 MW Sawalakote project on Chenab River issued by NHPC

Guru Ghasidas National Park Chhattisgarh

Chhattisgarh: Environment Ministry notified Bharat’s “56th Tiger reserve Guru Ghasidas-Tamor Pingla”

Load More

Latest News

Russian President Vladimir Putin and External Affairs Minister Dr. S. Jaishankar

EAM Jaishankar meets Russian President Putin & briefs bilateral developments; Extends PM Modi’s invite to BRICS Summit

Tamil Nadu Assembly

Tamil Nadu: TVK govt drops Parandur airport project, announces free bus travel and LPG cylinders

From students voice to political instrument?

PM addressing the Nation on the occasion of 80th Independence Day celebrations at Red Fort, in Delhi on August 15, 2026.

80th Independence Day Address of PM Modi: Walking the difficult path confidently

Representative Image

Beyond ‘Gen Z’: Why Bharat must reclaim its younger generation through ‘Samvad’ and ‘Kutumb Prabodhan’

JeM headquarters rebuilt in Bahawalpur, Pakistan

Pakistan: Destroyed in Operation Sindoor, JeM base rebuilt in 15 months; Exposes Islamabad’s eternal terror nexus

Dimagi Naxals: Decoding the cognitive virus

“A result of a gang war”: Former Envoy to Canada Sanjay Verma on Goldy Brar’s purported claim of hand in Nijjar killing

Tamil Nadu: Tirunelveli POCSO court awards death sentence to church pastor Abraham, for sexually assaulting minor girls

AI Generated Image

West Asia: 20,000+ Pakistanis deported; Gulf countries flag illegal entry, drug trafficking & national security threat

Load More
  • Privacy
  • Terms
  • Cookie Policy
  • Refund and Cancellation
  • Delivery and Shipping

© Bharat Prakashan (Delhi) Limited.
Tech-enabled by Ananthapuri Technologies

  • Home
  • Search Organiser
  • Bharat
    • Assam
    • Bihar
    • Chhattisgarh
    • Jharkhand
    • Maharashtra
    • View All States
  • World
    • Asia
    • Africa
    • North America
    • South America
    • Europe
    • Australia
  • Editorial
  • Operation Sindoor
  • Opinion
  • Analysis
  • Defence
  • Culture
  • Sports
  • Business
  • RSS @ 100
  • Entertainment
  • More ..
    • Sci & Tech
    • Vocal4Local
    • Special Report
    • Education
    • Employment
    • Books
    • Interviews
    • Travel
    • Health
    • Politics
    • Law
    • Economy
    • Obituary
  • Subscribe Magazine
  • Read Ecopy
  • Advertise
  • Circulation
  • Careers
  • About Us
  • Contact Us
  • Policies & Terms
    • Privacy Policy
    • Cookie Policy
    • Refund and Cancellation
    • Terms of Use

© Bharat Prakashan (Delhi) Limited.
Tech-enabled by Ananthapuri Technologies